Workday has been selected as our next ERP Financials and Human Resources product! Huron is our implementation partner and will work closely with all stakeholders as we begin taking our current processes and matching them in the new system. Additionally, training and support initiatives are in the works as well. Through collaboration with Workday, our implementation vendor, and campuses across the USM, we are working to ensure that everyone will have the opportunity to get very comfortable with Workday through multiple modalities of learning.
Want to know more about the Peoplesoft to Workday Transition?
- Join the conversation of Q&As in our Workday MS Team
- Email Ken Kundell or Robin Hoffman
- Interact with a Campus Workday Ambassador
Password: Kick-Off!
WORKDAY TIMELINE
Phase | Start Date | End Date | Weeks | Status |
---|---|---|---|---|
Readiness and Planning | August 2, 2021 | October 8, 2021 | 14 | Completed |
Architect | October 11, 2021 | March 18, 2022 | 22 | Completed |
Configuration & Prototype | March 21, 2022 | September 23, 2022 | 28 | In Progress |